We design new storeys and additions for office, shop and service buildings that stay within 3 storeys and 600 m² across every floor after the work, with no restaurant or other gathering place. An engineer designs the structure. Past either limit, the law requires an architect and an engineer; we check first.

In four numbers

The whole building with the addition built, every floor above grade. Past it, or past 3 storeys, an architect designs it.ontario.ca (opens in a new tab)
600 m²
The City's 2026 permit fee for a finished office addition; $20.77 for a shop.toronto.ca (opens in a new tab)
$24.46/m²
An addition this size or smaller to a non-residential building is exempt from parkland dedication.toronto.ca (opens in a new tab)
200 m²
The City's development charge on new ground-floor space only, since June 26, 2025.toronto.ca (opens in a new tab)
$805.64/m²

Does this sound like my property?

Most commercial additions start with one of these.

If one sounds like yours, say so in your request, and Rocco starts from there.
  • Stock photo of a one-storey red-brick commercial building with three tall steel-framed windows and a white garage door

    Building up a storey

    Your one- or two-storey shop or office building has zoning room for another storey, and you would rather build up than out.

  • Stock photo of a steel-framed building under construction, with excavators levelling the ground in front

    A rear or side addition

    You want a rear or side addition on an office or shop building, behind the front wall and away from the street.

  • Stock photo of a three-storey red-brick commercial building on a street corner, with large ground-floor shop windows on an overcast day

    Close to the 600 m² line

    You are not sure whether the enlarged building will stay within 600 m² and three storeys, or will need an architect.

  • Stock photo of a red steel frame for new storeys rising above an existing concrete floor

    A steel or glass storey

    You already picture a steel-framed or glass storey and need the engineer and the permit drawings lined up.

Does my project need an architect?

It depends on the size and use of the whole building.

Ontario's Architects Act sets the line at 3 storeys and 600 m², counting every floor above ground of the whole building after the work, not just your unit.
Stock photo of a one-storey brick office building with dark windows beside its parking lot

No architect needed

We design it

  • A building of up to 3 storeys and 600 m², used for offices, services or shops.
  • Interior work in a building of any size, when it leaves the structure, fire separations, exits, the main entrance and outside walls alone, and adds no floor space.
Stock photo of a five-storey office building in dark brick and glass above a landscaped entrance

Past the line

An architect designs it

  • A building of more than 3 storeys or 600 m².
  • A restaurant or bar, beyond the interior work. For up to 100 people, in a building within the line, an OAA Licensed Technologist may design it instead.

Not sure which side yours is on? We check it from the survey before any drawing starts.

Ask us to checkArchitects Act, s. 11 (opens in a new tab)

What will it take?

What the law requires for a commercial addition, and what we design.

The rules in plain English, each linked to its source, then every sheet in the set and each step from start to finish.

In short

  • The enlarged building measured against the 600 m² and three-storey limits before any design starts
  • The structure designed by a professional engineer, coordinated into one permit set
  • Our fee quoted in writing; the City's and the engineer's listed separately
Stock photo of a brick office building with rows of windows in low afternoon sun

Ontario's Architects Act lets a designer who is not an architect design an office, retail or personal-services building, without an architect supervising the work, only if, with the addition built, the whole building is no more than three storeys and no more than 600 m² of gross area (every floor above grade, measured to the outside of the exterior walls; a basement below grade doesn't count, but on a sloping lot a walk-out level can). Past either limit, an architect must design it and an engineer must do the engineering. A restaurant, bar or other place of assembly in the building needs an architect at any size, or an OAA Licensed Technologist for a restaurant for up to 100 people in a building of no more than three storeys and 600 m².

ontario.ca · Architects Act, R.S.O. 1990, c. A.26, ss. 11(3), 11(4) and 11(6); R.R.O. 1990, Reg. 27, s. 32.1 (opens in a new tab)

Who designs which part?

One permit set, with the right designer on every part.

On a commercial or industrial building, the Building Code and the Architects Act decide who may design each part. We draw the building where the law allows it, then fold the engineers' drawings into one set the City reviews together.
  • Stock photo of a pencil sketch of a building on paper, with markers and tape on a wooden deskOur part

    The building

    Layout, walls, exits, fire separations and the outside of the building

    Designed byArchitalcan, BCIN-registered, while the whole building stays within 3 storeys and 600 m² with no restaurant in it. Past that, an architect.

  • Stock photo of red steel beams and columns of a building frame against a pale sky

    Structure

    Beams, columns, footings, slabs and any new opening in a wall

    Designed byA professional engineer, or a designer registered in Building Structural.

  • Stock photo of a rooftop heating and cooling unit and two small condensers on a flat roof with a ladder and patches of snow

    Heating, cooling and ventilation

    Rooftop units, ductwork, exhaust and energy efficiency

    Designed byA professional engineer, or a designer registered in Building Services. Architalcan's HVAC class covers houses only.

  • Stock photo of red sprinkler pipes hung beneath the dark roof of a building under construction

    Sprinklers and fire alarm

    Sprinkler piping, alarm and detection

    Designed byEngineers, or designers registered for that work: Fire Protection; Detection, Lighting and Power.

  • Stock photo of two copper water pipes running up inside an opened wall

    Plumbing

    Washrooms, drains and water supply

    Designed byAn engineer, or a designer registered in Plumbing – All Buildings.

  • Stock photo of an electrical room lined with switchgear cabinets on both sides of a narrow aisle

    Lighting and power

    Lighting, emergency power and the electrical service

    Designed byAn engineer, or a designer registered for that work.

What does it cost?

Design and permit fees for a commercial addition: the City's, the engineer's and ours.

The City's bill, ours and the engineer's, kept apart. The City's permit fees follow its published 2026 schedules and are paid when each application is filed; development charges and parkland are due before the building permit is issued. Ours is quoted in writing; an engineer's or consultant's fee, where one is needed, is quoted on its own.

Paid to the City of Toronto

Building permit, City fee: offices
$24.46/m²
2026 rate for finished offices, banks, medical clinics and other finished business and personal-services space, on the floor area of the addition; minimum $214.79. Example: a 200 m² finished office storey is 200 × $24.46 = $4,892. Alterations to the existing floors are $12.45/m².
Building permit, City fee: shops
$20.77/m²
2026 rate for finished retail space; $15.76/m² for a retail shell. Alterations to existing retail floors are $11.53/m².
Zoning Applicable Law Certificate (ZAP)
$888.14
2026 City fee for a proposal on a building other than a house of 300 m² or less; $1,863.82 over 300 m². Covers up to three reviews and is credited against the permit fee when the permit application is filed with it on the City's Declaration Form – Use of Zoning Applicable Law Certificate.
Development charge, ground floor only
$805.64/m²
Charged by the City only on non-residential floor area on the ground floor, and paid when the building permit is issued. Rate in effect since June 26, 2025, not indexed in 2026. The Catholic school board's education development charge is separate; the City's page sets it on gross floor area without limiting it to the ground floor.
Parkland dedication, additions over 200 m²
2% of the land
For non-residential development the City takes 2% of the land to be developed, or cash in lieu of it, before the first above-grade building permit. An addition of 200 m² or less to an existing non-residential building is exempt (Municipal Code §§ 415-22, 415-24 and 415-30). Ask the City how it applies the 2% to an addition on your lot.

Paid to Architalcan

Design and permit set, our fee
In writing
Quoted in writing for your project.

Paid to the engineer or other designer

Structural engineer, their fee
Quoted separately
The engineer who designs the structure quotes their own fee; so do any mechanical, electrical, plumbing or sprinkler designers the new floor needs.

Who will draw it?

Architalcan Design, led by Rocco Schipano, BCIN-registered designer.

Where the law requires an architect or engineer, they design and seal that work. Rated 5.0 from 273 reviews on HomeStars.
Rocco Schipano holding the HomeStars Best of the Best 2023 award

Renovation of a semi in Toronto

Rocco was efficient and effective. He worked closely with us to ensure the design meets our needs and recommended valuable solutions that we previously weren't aware of. We got the permit within a reasonable amount of time despite submitting it just before the holidays.

HomeOwner · Jan 17, 2025
Read all 273 on HomeStars (opens in a new tab)
Registration
BCIN 25897 – 41741 Look up the BCIN
Classes
House · Small Buildings · Large Buildings · HVAC-House
On the drawings
The designer's name, BCIN and signature, as Toronto Building requires; engineer-designed sheets carry the engineer's seal. Why the City asks (opens in a new tab)
About Rocco and the firm

How do I start?

Get a written quote for your commercial addition.

Send the address, what the building is used for, how many storeys it has and roughly how big each floor is, and what you want to add. Rocco replies in writing with what the project needs and a quote.

Step 2 of 3 · Property

Project:Commercial

Where is the property?
Do you have a property survey?

A survey lets us confirm setbacks and buildable area from the start. No survey? We'll tell you how to get one.

BCIN registered · Insured · 20+ years in Toronto

Questions before you send it

Can you design a new storey on my building?

Yes, if the whole building stays within three storeys and 600 m² of gross area once the storey is added, and no part of it is a restaurant, bar or other place of assembly. Two existing floors of 200 m² plus a new 200 m² storey come to exactly 600 m², which is still within the limit. Anything more, or a fourth storey, and the Architects Act calls for an architect and an engineer, who also carry out the general review (the designer's site reviews during construction) that the Building Code then requires. A professional engineer designs the structure either way. The zoning height and storey limits have to allow it too.

Is the 600 m² the same as the zoning floor area?

No. The Architects Act (and the Building Code's table for the designer's site reviews) counts every floor above grade, measured to the outside of the exterior walls. The Code's Part 9 test uses only the largest floor. The zoning by-law's gross floor area counts floors above and below ground (800.50(320)), and in a CR zone it then subtracts areas such as below-ground parking, basement storage and mechanical rooms, elevator shafts and exit stairs before the floor space index is worked out (40.5.40.40). The site plan exemption's 600 m² is different again: it is the addition alone, measured as zoning gross floor area, and must be under 600 m². A building can pass one test and fail another, so all of them are worked out at the size check.

Does my addition need site plan approval?

Not if it is under 600 m² on its own, kept out of the front yard and free of the uses the by-law lists. Two cautions. The exemption does not cover a use the zoning permits only with conditions, and in the CR zone the by-law lists retail stores and eating establishments that way (40.10.20.20), so don't assume a shop addition is exempt until the City confirms it. (A building with apartments follows a separate test, in which a retail store is allowed.) And the City can still require site plan approval near a rail line or a valley, or for access, safety or a road or laneway widening.

Who designs the structure?

A professional engineer. Our BCIN classes don't include structural design for commercial buildings, and even in small buildings the Building Code requires an engineer to design any underpinning, or a foundation dug below a neighbouring building's footings and close enough to disturb the soil under them (within the soil's angle of repose, drawn from the bottom of those footings; Division C, Article 1.2.1.2). The engineer's drawings and ours go to the City as one coordinated set.

How much glass can the new storey have?

It depends on each wall's limiting distance: its distance to the property line, or to the centre line of the street or lane it faces. Under Part 9 of the Building Code, a wall less than 1.2 m from that line can have no unprotected openings (glazing or openings that aren't fire-rated). Farther away, the share allowed rises with distance and falls as the wall gets bigger, and a shop is allowed about half what an office is (9.10.14.4). A sprinklered building, or glazing of wired glass in steel frames or glass block, may have up to twice as much, and a storey at street level facing a street, with a limiting distance of at least 9 m, isn't limited. The wall is measured from the ground to the ceiling of the top storey, so a new storey can change the numbers for the windows below it, unless the floors are fire separations rated at least 45 minutes, which lets each storey be counted on its own (9.10.14.2).

Will there be development charges?

Toronto charges non-residential development charges (a City charge on new development, paid once) only on non-residential floor area on the ground floor, at $805.64 per m² (the rate in effect since June 26, 2025), payable when the building permit is issued. A ground-floor addition is charged on its area. Read as written, a storey above the ground floor adds no ground-floor area. The City also collects the Toronto Catholic District School Board's education development charge on non-residential gross floor area: $1.67 per sq ft until December 2, 2026 and $1.77 from December 3, 2026. The City's page doesn't limit that one to the ground floor, so ask the City whether either charge applies to your addition before you budget.

Does more floor area mean more parking or loading?

It can mean loading and bicycle parking. A shop or personal service shop needs no loading space under 500 m² of gross floor area and one Type B space (11.0 m by 3.5 m, 4.0 m clear, or 4.4 m in Policy Area 1 where the building has no apartments) from 500 m²; an office needs one Type B from 500 m² too. An addition must provide any loading space it adds or get a minor variance, though in a CR zone under Development Standard Set 2 or 4 (SS2 or SS4 in the zone label), a lot with a lot area under 1,000 m² is exempt (220.5.200.40). Under Zoning By-law 569-2013 an addition must also meet Chapter 230's bicycle parking requirement (and, where required, shower, change and bicycle maintenance facilities) unless a minor variance authorizes otherwise (230.5.10.11). Car parking for these uses has maximums, not minimums, under Zoning By-law 569-2013 (accessible spaces aside), but an existing building's lawful number of spaces may not be reduced (200.5.10.11), which matters if the addition goes over the parking lot.

What if the zoning doesn't allow the height?

Then the storey needs a minor variance from the Committee of Adjustment, which may authorize one only if it finds the variance minor, desirable for the appropriate development or use of the land, and in keeping with the general intent of the zoning by-law and the Official Plan (Planning Act, s. 45(1)). A height increase too large to count as minor needs a zoning by-law amendment (a rezoning) instead. The size check and zoning review tell you which before any design work.