Industrial · Unit alterations

Industrial unit alterations in Toronto. Offices, washrooms, new walls.

We design the changes inside an industrial unit, such as offices and washrooms on the shop floor or a demising wall that splits one unit into two, and draw them for the permit. In a building over 3 storeys or 600 m², work on the structure, fire separations or exits needs an architect or engineer, so we check first.

In four numbers

The City's 2026 fee for industrial space, per m² of the area altered, mezzanines included.toronto.ca (opens in a new tab)
$11.53/m²
The whole building, not your unit. Past it, or past 3 storeys, work beyond the interior needs an architect or engineer.ontario.ca (opens in a new tab)
600 m²
Up to this area, or 10 people, one washroom for everyone can be enough in industrial space.ontario.ca (opens in a new tab)
300 m²
The City's surcharge when work starts before the permit: half the fee, at least $214.79.toronto.ca (opens in a new tab)
+50%

Does this sound like my property?

Most industrial unit alterations start with one of these.

If one sounds like yours, say so in your request, and Rocco starts from there.
  • Stock photo of an empty new industrial unit with a polished floor, yellow-guarded steel columns and high-bay lights

    Offices or washrooms inside

    You want offices, a lunchroom or washrooms built inside your warehouse or shop floor.

  • Stock photo of a single-storey steel building with a row of white roll-up doors on a gravel yard

    Splitting or joining units

    You are splitting one unit into two, or joining two, and need to know what the wall between them must be.

  • Stock photo of four truck loading docks with dock seals and yellow bollards on a cream-coloured warehouse wall

    A new loading or entry door

    You need a new loading or entry door cut into an exterior wall, and need to know who must design the opening and its structure.

  • Stock photo of white steel storage racking loaded with cardboard boxes in a bright warehouse

    A mezzanine or racking

    You are adding a mezzanine or racking with walkways, and need the engineer's design fitted into the unit's exits, sprinklers and permit set.

  • Stock photo of the white roof of a very large warehouse seen from the air, with parking and fields around it

    A unit in a larger building

    Your unit is in a building of more than three storeys or more than 600 m² gross area (every floor above ground of the whole building, not just your unit), and you need to know what can be drawn without an architect or engineer.

Does my project need an architect?

It depends on the size and use of the whole building.

Ontario's Architects Act sets the line at 3 storeys and 600 m², counting every floor above ground of the whole building after the work, not just your unit.
Stock photo of a small concrete-block warehouse with two truck loading doors and a parking lot in front

No architect needed

We design it

  • A building of up to 3 storeys and 600 m², used for industry, offices or shops.
  • Interior work in a building of any size, when it leaves the structure, fire separations, exits, the main entrance and outside walls alone, and adds no floor space.
Stock photo of an aerial view of low commercial and industrial buildings, parking lots and empty lots beside a highway

Past the line

An architect or engineer designs it

  • A building of more than 3 storeys or 600 m².
  • A building made to house an engineered process, at any size: a professional engineer designs it.

Not sure which side yours is on? We check it from the survey before any drawing starts.

Ask us to checkArchitects Act, s. 11 (opens in a new tab)Professional Engineers Act, s. 12 (opens in a new tab)

What will it take?

What the City and the Building Code ask of a unit alteration, and what we draw.

The rules in plain English, each linked to its source, then every sheet in the set and each step from start to finish.

In short

  • Whether an architect or engineer must design or review any part, checked against the whole building first
  • Engineers and qualified designers for structure, racking, sprinklers, HVAC and plumbing, coordinated into one set
  • Our fee quoted in writing; City fees listed separately
Storage racking installed in a finished industrial unit

The Architects Act needs no architect for the design of an alteration to a building of up to three storeys and 600 m² gross area as altered, used only for industrial, business, personal services, mercantile, residential or agricultural occupancy. Gross area counts every floor above grade of the whole building, measured to the outside of its exterior walls (or to the centre of a firewall that no access opening or building service passes through), so a 200 m² unit can sit in a 5,000 m² building. Past either limit, an industrial building's design comes from an architect or a professional engineer, with any engineering by an engineer; where another use in it, such as offices, takes up more than 600 m², from an architect and an engineer, though an engineer may still design the industrial part.

ontario.ca · Architects Act, ss. 11(3)(a), 11(4) rules 2 and 3, and 11(6) (e-Laws) (opens in a new tab)

Who designs which part?

One permit set, with the right designer on every part.

On a commercial or industrial building, the Building Code and the Architects Act decide who may design each part. We draw the building where the law allows it, then fold the engineers' drawings into one set the City reviews together.
  • Stock photo of a pencil sketch of a building on paper, with markers and tape on a wooden deskOur part

    The building

    Layout, walls, exits, fire separations and the outside of the building

    Designed byArchitalcan, BCIN-registered, while the whole building stays within 3 storeys and 600 m². Past that, an architect or a professional engineer.

  • Stock photo of red steel beams and columns of a building frame against a pale sky

    Structure

    Beams, columns, footings, slabs and any new opening in a wall

    Designed byA professional engineer, or a designer registered in Building Structural.

  • Stock photo of a rooftop heating and cooling unit and two small condensers on a flat roof with a ladder and patches of snow

    Heating, cooling and ventilation

    Rooftop units, ductwork, exhaust and energy efficiency

    Designed byA professional engineer, or a designer registered in Building Services. Architalcan's HVAC class covers houses only.

  • Stock photo of red sprinkler pipes hung beneath the dark roof of a building under construction

    Sprinklers and fire alarm

    Sprinkler piping, alarm and detection

    Designed byEngineers, or designers registered for that work: Fire Protection; Detection, Lighting and Power.

  • Stock photo of two copper water pipes running up inside an opened wall

    Plumbing

    Washrooms, drains and water supply

    Designed byAn engineer, or a designer registered in Plumbing – All Buildings.

  • Stock photo of a long warehouse aisle lined with blue and orange pallet racking, with loading doors along the far wall

    Racking with walkways

    Storage racking with raised platforms or walkways for staff

    Designed byA professional engineer, as the Building Code requires, whatever the building's size.

What does it cost?

Permit and design fees for an industrial unit alteration: the City's, and ours.

The City's bill, ours and the engineer's, kept apart. The City's fees follow its published 2026 schedules and are paid when each application is filed. Ours is quoted in writing; an engineer's or consultant's fee, where one is needed, is quoted on its own.

Paid to the City of Toronto

Interior alteration permit, industrial space
$11.53/m²
2026 City rate for industrial space (Group F), per m² of the area receiving the work, mezzanines included. Example: a 300 m² unit alteration is 300 × $11.53 = $3,459.
Interior alteration permit, office space
$12.45/m²
2026 City rate for business space (Group D). For a floor that mixes uses, the by-law lets the City use the rate of any use on it, except a use under 10% of the floor area.
Minimum City permit fee
$214.79
2026 minimum for any permit: it covers up to about 18.6 m² of industrial work.
Plumbing and HVAC permits, filed with it
No extra fee
Toronto Building charges no additional fee for the related plumbing permit filed with the building application, apart from the items it lists separately, such as site-servicing pipes or $92.79 for each backflow prevention device. The related HVAC permit costs nothing more unless it includes a specialty system.
Zoning Applicable Law Certificate
$888.14
2026 City fee for alterations to a building other than a house, up to 300 m²; $1,863.82 over 300 m². Credited against the permit fee when the permit application is filed with it and the City's Declaration Form – Use of Zoning Applicable Law Certificate.
Work started before the permit
+50%
City surcharge of half the permit fee or $214.79, whichever is greater, up to $29,456.99 per permit (2026).

Paid to Architalcan

Design and permit set, our fee
In writing
Quoted from the unit plan, the building and the scope of the work.

Paid to the engineer or other designer

Architects, engineers and other designers
Quoted on their own
Where an architect, an engineer, or a designer qualified for sprinklers, HVAC or plumbing must design or review part of the work, their fee is separate from ours.

Who will draw it?

Architalcan Design, led by Rocco Schipano, BCIN-registered designer.

Where the law requires an architect or engineer, they design and seal that work. Rated 5.0 from 273 reviews on HomeStars.
Rocco Schipano holding the HomeStars Best of the Best 2023 award

Renovation of a semi in Toronto

Rocco was efficient and effective. He worked closely with us to ensure the design meets our needs and recommended valuable solutions that we previously weren't aware of. We got the permit within a reasonable amount of time despite submitting it just before the holidays.

HomeOwner · Jan 17, 2025
Read all 273 on HomeStars (opens in a new tab)
Registration
BCIN 25897 – 41741 Look up the BCIN
Classes
House · Small Buildings · Large Buildings · HVAC-House
On the drawings
The designer's name, BCIN and signature, as Toronto Building requires; engineer-designed sheets carry the engineer's seal. Why the City asks (opens in a new tab)
About Rocco and the firm

How do I start?

Get a written quote for your industrial unit.

Send the address, what the unit is used for now and will be, its area, the building's size if you know it, and the landlord's floor plan if you have one. Rocco checks the building and the zoning and replies in writing with what the work needs and a quote.

Step 2 of 3 · Property

Project:Industrial

Where is the property?
Do you have a property survey?

A survey lets us confirm setbacks and buildable area from the start. No survey? We'll tell you how to get one.

BCIN registered · Insured · 20+ years in Toronto

Questions before you send it

Do I need a building permit to build offices and washrooms in my unit?

Yes. Toronto Building lists adding or removing walls (changing room sizes or uses) and installing or modifying heating or plumbing among the work that needs a permit. Industrial interior alterations of up to 300 m², with no change in use, no change in patron area, no active permit for the building shell and no heritage approval needed, can go through Express Services, where the City's goal is an examiner's review within three days of intake. Starting before the permit adds a City surcharge of half the permit fee, at least $214.79.

Do I need an architect or an engineer?

It depends on the whole building and on what the work touches. In an industrial building of up to three storeys and 600 m² gross area, neither the Architects Act nor the Professional Engineers Act requires one, unless the building is designed to house, or is part of, a process, apparatus or facility whose design is engineering work; then an engineer designs it. In a bigger building, the Architects Act needs no architect to design interior work that leaves the structure, fire separations and fire safety systems, the main entrance and public corridors, exits and exterior walls alone and adds no mezzanine; beyond that, an architect or engineer designs it. That interior exception is in the Architects Act only: the Professional Engineers Act has no matching one outside a dwelling unit, and the Building Code lists the alteration of an industrial building past those limits as one an architect or professional engineer reviews during construction. So in a bigger building we confirm with Toronto Building, before drawing starts, whether an architect or engineer must design, seal or review any part. In any building, an engineer designs racking with walkways. Under the Building Code Act, the City's chief building official issues a permit unless, among other things, the law requires an architect's or engineer's design and the work was not so designed.

We're splitting the unit in two. What does that involve?

A demising wall built as a fire separation between the two (45 minutes in a Part 9 building, 1 hour or in some cases 45 minutes in a Part 3 one), and a look at loading. In an employment industrial zone, Toronto's zoning counts loading spaces for each industrial unit (the part of the building one owner or tenant controls) from that unit's interior floor area: for manufacturing or warehouse use, none under 100 m², one small Type C space from 100 m², one Type B from 500 m² and one large Type A from 1,000 m² (two from 5,000 m²), subject to any site-specific exception or older zoning by-law that still applies to the address. In a building over three storeys or 600 m² gross area, a new fire separation takes the work outside the Architects Act's interior exception, so an architect or engineer designs it.

Can we cut a new loading door or entry door into an exterior wall?

With a permit: Toronto lists new doors or windows where there were none, and enlarging or moving existing ones, among the work that needs one, and outside houses even replacing a window or door does. The structure around the opening (the lintel or frame that carries the wall above) is designed by a professional engineer or, in a building small enough to need neither an architect nor an engineer, a designer registered in the Building Structural class (not a class we hold). The Building Code also caps the total area of openings in a wall that faces a property line, by how far the wall sits from it (its limiting distance). In a building over three storeys or 600 m² gross area, work on an exterior wall is outside the Architects Act's interior exception, so an architect or engineer designs it.

Can we add a mezzanine for offices or storage?

It can be done, but it changes more than the floor plan. A mezzanine (a partial floor built within the height of a storey) is not counted as a storey if mezzanines take up no more than 10% of the floor area (and of the suite), or no more than 40% of the room's open area with the space above left open: no walls higher than 1,070 mm, apart from an enclosed room of up to 10% of that open area, such as a small office, that does not block the view between the open space above the mezzanine and the room. A second mezzanine level counts as a storey. In a Part 9 building, its area is added to the floor area of its storey when the occupant load is worked out; it is always added to the City's fee area. Its structure is designed by a professional engineer or, in a building small enough to need neither an architect nor an engineer, a designer registered in the Building Structural class (not a class we hold), and in a building over three storeys or 600 m² gross area it is outside the Architects Act's interior exception.

Does storage racking need an engineer?

Racking with platforms or walkways for people does, in any building: a professional engineer designs it and reviews it being built, the floor area needs sprinklers to NFPA 13, and each walkway level needs at least two exits with few exceptions. Racking with no platforms or walkways is outside the Building Code's definition of a shelf and rack storage system, so those rules do not apply to it; whether it belongs in your permit is something to settle with Toronto Building before the application goes in.

We want offices inside the unit. Is that a different use?

Not necessarily: the Building Code counts subsidiary occupancies that are an integral part of the principal one as part of it. Where offices are a separate major occupancy, the Code's Part 3 table asks for no fire separation between them and medium- or low-hazard industrial space, and 3 hours from high-hazard space; separate tenants still need the separation between suites. Office is on the list of permitted uses in Toronto's E (employment industrial) zone, though any address can carry its own exceptions. In a building over three storeys or 600 m² gross area, the design must come from an architect or engineer while no other use takes up more than 600 m² (apart from interior work within the Architects Act's exception); past that, from an architect and an engineer, though an engineer may still design the industrial part. Where offices make up at least 10% of a mixed floor area, the City may charge that area at the office rate ($12.45/m²) or the industrial rate ($11.53/m²).

What if the unit's use changes too?

The Building Code lists which changes need a permit even with nothing built: among them, low-hazard to medium-hazard industrial, medium- or low-hazard industrial to high-hazard industrial, and industrial space to a shop, a restaurant or other assembly use, or homes. A change from one industrial use to low-hazard industrial, from high- to medium-hazard, or from medium- or low-hazard industrial to offices is not on the Code's list, as long as the whole suite changes. Toronto Building's own page goes further: “Even if no construction is proposed, if a change of use is proposed a building permit is required”, so we confirm with the City first. When the alteration permit includes the new use, it covers the change, but Express Services do not take a change in use. Interior conversions to a use the zoning already permits are exempt from site plan approval up to 1,000 m² of altered floor area, unless the conversion also includes a drive-through, an entertainment place of assembly, a place of assembly, a place of worship or a transportation use. Between industrial uses, the exemption applies only where no asphalt, cement or concrete batching plant, recovery or recycling facility, salvage yard or waste transfer station is involved and, where Zoning By-law 569-2013 applies, no use it permits only with conditions. Site plan approval is still required where the Official Plan calls for a road widening, and the City may require it in other cases, such as a site within 300 m of a railway line. Our change of use page covers the rest.