Most older Toronto basements are too low to live in comfortably. Getting more height means taking the floor down, and once the dig goes below the bottom of the house's footings, either new footings go in underneath them or a sloped bench is left along the walls. New footings underneath is underpinning, the usual way to lower a basement. It is structural work under a house people live in, so it starts with a design and a permit. This guide covers both, along with when the City requires an engineer and what the work costs.
- City permit fee per linear metre of underpinning, 2026
- $12.37
- Underpinning height without side support, past which professional design is required
- 1.2 m
- City's Express Services review goal, in business days
- 3 days
- Minimum ceiling in a secondary suite, about 6'5"
- 1.95 m
What underpinning is, and when you need it
Toronto Building describes underpinning as a way to deepen the foundation of an existing house by building new footings beneath the existing ones. Its guide names three reasons to do it:
Dig the floor down for more ceiling height, with new footings under the walls so the house stays supported at the new depth.
Strengthen a foundation that needs it, even without lowering the floor. The City still wants the work drawn in numbered stages.
A stair down to a new door below grade, with the walls beside it underpinned. It has its own permit, charged at the same rate per linear metre.
The work goes in short sections so the wall is only ever undermined over a short length. People in the trade call each section a pin. Pins are dug in a set order, never two side by side, and each one is formed and poured before the soil next to it is opened.


Basement lowering: underpinning or benching?
There are two ways to take a basement floor down:
New footings go in beneath the existing ones, in numbered stages. The new floor runs wall to wall at the lower level, so you keep the full room.
The existing footing stays as it is. The new floor is poured lower in the middle, and a sloped or stepped concrete bench is left along the walls so the soil under the old footing isn't disturbed.
Benching avoids digging under the house, but it costs floor: the bench takes width off every wall, and the deeper you go, the wider it gets. How wide depends on the soil. For a drop of a few inches, benching can be the budget route. For a real change in ceiling height, underpinning is usual. The permit drawings show which one, with the stages numbered.
How far down do you need to go?
Start from the height you want, measured to the lowest thing overhead: the joists, a beam or a duct. Then remember the dig goes deeper than the finished floor. The Building Code asks for at least 100 mm of clean gravel under a basement floor and a concrete slab at least 75 mm thick, which is about 7" in all before insulation and the floor finish (9.16.2.1, 9.16.4.3).
Which height counts depends on how the basement will be used and how old the house is:
| How the basement is used | Minimum height | Where the rule comes from |
|---|---|---|
| A second unit in a two-unit house (secondary suite) | 1.95 m ceiling, 1.85 m under beams and ducts | Building Code 9.5.3.1, with no allowance for older houses |
| Any lived-in room in a basement | 1.95 m over at least half the floor | Toronto Property Standards, § 629-25 D |
| Basement space in your own home, house under 5 years old | 2.1 m over 75% of the area, 1.95 m under beams and ducts | Building Code Table 9.5.3.1 |
| Rooms in your own home, house 5 years or older | 1.95 m over the required floor area and along the way out, or 2.03 m over at least half of it | Building Code Part 11, alternative C105 |
In a newer house, some rooms have their own line in the Code's table: a living room, dining room or kitchen needs 2.3 m over 75% of its area and 2.1 m at any point, and a bedroom 2.3 m over half its area or 2.1 m over all of it. Toronto's Property Standards also say no basement may be used as a habitable room or a home unless its way out, light, ventilation and ceiling height all comply (§ 629-4 B).
If the basement might ever become a second unit, design to the suite heights now. Lowering the floor a second time is not an option anyone wants. Those heights are for a house with two units; a basement unit in a triplex or fourplex is held to different rules, so check before the drawings start. Our legal basement apartment guide covers the rest of what a suite needs.

When the City requires a Professional Engineer
Toronto Building's underpinning guide requires professional design and review on site in three cases, and names a Professional Engineer (P.Eng.) outright for the first:
- Below a neighbour's footing: the new foundation goes below the level of an adjacent building's footing and inside the soil's angle of repose (explained below). A Professional Engineer designs it, reviews it on site and seals the drawings.
- More than 1.2 m without side support: the underpinning has more than 1.2 m (about 4 ft) of what the City calls laterally unsupported height.
- Clay or silt: the soil under the house is clay or silt.
In each case the professional signs the City's Commitment to General Reviews form, and the owner fills in its Part A. For the last two, the City's form allows an architect, an engineer or another qualified consultant; on underpinning, that professional is usually an engineer.
An engineer's seal can also speed up the review. Under Toronto Building's Reliance on Professional Engineer's Seal program, house projects with up to two units can qualify for an expedited review of the sealed parts, where the City relies on the seal for their Building Code compliance. The engineer lists what they are responsible for on the Assumption of Responsibility for Engineering Content form. Zoning is still reviewed in full.
The angle of repose, in plain terms
Soil next to a footing can stand at a certain slope before it starts to slide. The steepest stable slope is the angle of repose. The City warns that disturbing soil anywhere inside it can make the soil fail and cause serious damage that is hard to repair. Its sketch gives two common cases: dense sand stays stable at 1 down for every 2 across, and firm clay at 7 down for every 10 across. Where the dig would go past those slopes, or the soil type is unknown, the City says to have a professional prepare the design drawings.
Here is what that means next door. Say the edge of the neighbour's footing is about 1.2 m from the outside edge of your dig, new footing included, and the soil is dense sand. Their stable slope drops 0.6 m over that gap, so digging more than about 0.6 m below the bottom of their footing reaches inside it. Nobody knows how deep a neighbour's footing is until it is found, which is why the City wants the distance to the neighbours' foundations, and their depth, on the foundation plan.


What the City asks to see
The application goes in as PDFs through Toronto Building's online Application Submission Tool. Every sheet is drawn to scale, fully dimensioned, signed and dated, and a qualified designer adds their name, registration number, qualification number and a statement taking responsibility for the design. For underpinning, the City's guide asks for:
- Site plan on a current survey: property lines, lot area, any easements, and the distances from the house to the property lines and to the neighbouring buildings.
- Foundation plans, existing and proposed: where the underpinning goes, the support columns and framing above, the stages numbered in order and the linear metres of underpinning. Where it applies, the distance to the neighbours' foundations and how deep they go.
- Floor plans for each level, fully dimensioned, with existing and proposed uses, smoke and carbon monoxide alarms, plumbing fixtures, partitions and framing.
- Sections showing the footing and wall details, the depth of underpinning, the outside ground level above the new basement floor, and the floor-to-floor, floor-to-ceiling and overall heights.
- Construction details for the floor and wall assemblies, plus stairs, landings, guards and handrails.
- Forms: the Application to Construct or Demolish, Schedule 1 Designer Information, the Assumption of Responsibility for Engineering Content form for engineer-sealed sheets, the Commitment to General Reviews where professional design is required, the Tree Declaration where trees could be damaged, and the Rental Renovation Licence Screening Form, which checks whether the work also needs a rental renovation licence under Municipal Code Chapter 662.
The City also asks that no personal information, such as the owner's name or phone number, goes on the drawings, because permit plans can be disclosed to the public.
A new basement entrance has its own permit and guide, charged at the same $12.37 per linear metre of underpinning. It adds a summary of the zoning provisions, permitted and proposed: lot area, floor area, coverage and grade elevations, plus parking, driveways, landscaping and accessory buildings. The drawings show the underpinning next to the entrance, the stairs, the landing at the bottom and the guards with their connections.


What underpinning costs
The cost has four parts: the City's fees, the design, the engineer and the construction.
The City's fees
In 2026 the underpinning permit is $12.37 per linear metre of underpinning, with a $214.79 minimum for all work. The minimum covers up to about 17 linear metres. No permit is issued until the City's fees are paid.
| Underpinning | City fee |
|---|---|
| 17 linear metres or less | $214.79 (the minimum) |
| 25 linear metres | $309.25 |
| 34 linear metres (all four walls of a 6 m × 11 m basement) | $420.58 |
| 45 linear metres | $556.65 |
- Finishing the basement: the City's rate for finishing a basement in a house is $6.20 per m², so 60 m² is $372.00.
- If the basement becomes a second unit: interior alterations are $11.53 per m², plus $56.33 for each new unit.
- Plumbing: $23.20 per fixture in a single-family house, $38.67 for each backwater valve or sump with a pump, and $214.79 flat for new or replaced drain pipes under the floor.
- Heating: if ducts or the furnace move, ductwork alterations are $214.79 flat under the City's mechanical permit.
- Starting before the permit is issued: an extra 50% of the permit fee or $214.79, whichever is greater, up to $29,456.99 per permit.
Design, engineering and construction
We quote the design and permit set in writing after looking at the house, and the engineer's own fee is quoted alongside it. The construction cost depends mostly on these:
- How far down: a deeper drop means deeper pins, more soil out and, past 1.2 m without side support, professional design.
- How many linear metres: the walls being underpinned, and how many stages that makes.
- The soil and water: clay or silt means professional design; water in the dig slows the work and may need pumping.
- Getting soil out: in a city house the soil usually leaves through a window or a door, by hand or on a conveyor.
- What sits on the floor: the furnace, water heater and drains have to be supported or moved while the floor is out.
- The new floor: drains, a sump pit where needed, gravel, insulation and the new slab.
- An entrance or a suite: a stair down to a new door, or the fire separation, alarms and ventilation a suite needs.


Timeline: from site visit to a closed permit
- 01Site visit and measure
Today's clear height, the footing depth where it can be seen, the distance to the neighbours' walls, and any signs of soil type or water.
- 02Route and engineer
Underpinning or benching, and which of the City's rules for professional design applies. The engineer is brought in at this point.
- 03Drawings and forms
Foundation plans with numbered stages and linear metres, sections to the new depth, floor plans and details, with the engineer's sealed sheets and the forms.
- 04City review
Underpinning and basement walkouts on a house with up to two units, and no open permit for a new house or an addition, can go through Express Services. There the City aims to review within 3 business days after the application is taken in. Otherwise a house with up to two units goes to the House Stream: 10 business days once the application is complete, which needs an issued Zoning Applicable Law Certificate ($644.38 for alterations to houses in 2026). A triplex or fourplex goes to the Small Building Stream, 15 business days.
- 05Construction in stages
The contractor digs and pours in the numbered order. The engineer tests and reports at the first and last stages at minimum.
- 06Inspections
Call for the footings inspection when the forms are in, before any concrete; the foundation inspection when it is complete; and the plumbing inspections before drains are buried. Work done in stages may need more than one of each. The City inspects within two business days of a request, and the stamped permit plans have to be on site.
- 07Close the permit
The final inspection closes the permit once the work is complete.
Where to start
Measure today's clear height to the lowest joist, beam or duct, and decide the height you want. Photograph the basement walls, the floor and any cracks or damp spots, and note whether the house is detached, semi-detached or a row house. Send them through our underpinning page. Rocco replies in writing with the route, whether an engineer must design it, and the quote.
Questions people ask
01Do I need a permit to underpin my basement in Toronto?
Yes. Toronto Building issues a building permit for underpinning the foundation of an existing house, whether to lower the basement or to strengthen the foundation. A new basement entrance has its own permit, charged at the same rate per linear metre of underpinning. The drawings show the stages numbered in order and the linear metres of underpinning, and the application goes in as PDFs through the City's online tool.
02How much does basement underpinning cost in Toronto?
The City's 2026 permit fee is $12.37 per linear metre of underpinning, with a $214.79 minimum, so 34 linear metres (all four walls of a 6 m by 11 m basement) is $420.58. On top of that come the design and permit drawings, the engineer, and the construction. Construction depends most on how deep you go, how many metres of wall are underpinned, the soil and water, and how the soil gets out of the house.
03Do I need an engineer for underpinning?
On every job, a Professional Engineer tests and reports at the first and last construction stages, which the City needs to pass inspections. A Professional Engineer must also design the work and review it on site when the new foundation goes below a neighbour's footing inside the soil's angle of repose. Professional design and site review are also required when the underpinning has more than 1.2 m of height without side support, or when the soil is clay or silt.
04Can I underpin a semi-detached house?
Yes, but the footing under the shared wall carries your neighbour's house too, so going below it means an engineer designs the work and reviews it on site. Toronto Building's interior alterations guide says that if a party wall is involved, a permit must be issued for every property it separates. Talk to your neighbour before the drawings start.
05How long does an underpinning permit take?
Underpinning on a house with up to two units, and no open permit for a new house or an addition, can go through Express Services, where the City aims to review within 3 business days after the application is taken in. In the House Stream, complete applications are reviewed within 10 business days. An incomplete application has no review clock, so a complete set is the fastest route.
06What is the difference between underpinning and benching?
Underpinning builds new footings under the existing ones, in numbered stages, so the lower floor runs wall to wall. Benching leaves the footing alone and lowers only the middle of the floor, leaving a concrete bench along the walls. Benching avoids digging under the house but takes floor width from every wall, and the deeper the drop, the wider the bench.
Sources
- 01Toronto Building: Residential Underpinning permit guide (opens in a new tab)
- 02Toronto Building: Residential Basement Entrances permit guide (opens in a new tab)
- 03Toronto Building: Interior Alterations permit guide (opens in a new tab)
- 04Toronto Building: building permit fees (effective January 1, 2026) (opens in a new tab)
- 05Toronto Building: Building Permit Review Streams (opens in a new tab)
- 06Toronto Building: Reliance on Professional Engineer's Seal (opens in a new tab)
- 07Toronto Building: When to Call for Inspection of Small Buildings (opens in a new tab)
- 082024 Building Code Compendium, Div. B, Part 9 (Articles 9.5.3.1, 9.16.2.1 and 9.16.4.3, Table 9.5.3.1) (opens in a new tab)
- 092024 Building Code Compendium, Div. B, Part 11 (Article 11.5.1.1, Table 11.5.1.1.-C, C105) (opens in a new tab)
- 102024 Building Code Compendium, Div. A, Article 1.3.3.3B (Part 11 for buildings five years or older) (opens in a new tab)
- 11Toronto Municipal Code Chapter 629, Property Standards (§ 629-4 B, § 629-25 D) (opens in a new tab)
- 12City of Toronto: Basement Flooding Protection Subsidy Program (opens in a new tab)
Rules and fees change. We verify them on every project before drawings start.