A second storey is the biggest addition most Toronto houses can take, and it leaves the yard alone: it goes up on the house's own footprint. This guide covers what it costs (the City's charges to the cent, and what drives the rest), what the zoning allows, whether the house can carry another floor, and how long it takes from the first measure to a closed permit. We design additions and file the permits for them.
- City permit fee per m² of new floor area, 2026
- $18.56
- Height limit in detached-house zones where the overlay map sets none
- 10.0 m
- Building Code's basic footing width under exterior walls carrying two floors
- 350 mm
- City review of a complete House Stream application, in business days
- 10 days
Up, back or move?
Most families who need more room weigh three routes on the lot they have:
A new floor over the whole house. The most space, and the yard stays as it is, but the roof comes off and the foundation has to carry the extra floor.
A new floor over part of the house, often the back. Less space, a smaller roof opening and a lighter load on the foundation.
One or two storeys built out the back. The existing roof stays on, but the yard gets smaller and the rear yard and building length rules apply.


What the zoning allows on top of your house
Toronto's Zoning By-law 569-2013 sets the space a house may fill. For a detached house in a Residential Detached (RD) zone, these are the rules that shape a second storey. Semi-detached (RS), townhouse (RT) and other zones carry their own versions of the same rules, and site-specific exceptions in the by-law's Chapter 900 can change any of them on a given lot.
- Height: the number after “HT” on the City's Height Overlay Map, or 10.0 m where the map shows none (10.20.40.10(1)).
- Main walls: the higher of 7.0 m, or 2.5 m below the height limit: 7.5 m under a 10.0 m limit. At least 70% of the width of each side wall has to stay at or under it, or else 40% to 60% of the width of the front and rear walls, depending on the lot's frontage (10.20.40.10(2)). It's why so many second storeys finish with a sloped roof.
- Flat roofs: with a roof flatter than 1 in 10 over more than half its area, all the main walls are capped at the higher of 7.2 m or 2.5 m below the height limit (7.5 m under a 10.0 m limit). Walls above that are allowed only where they are set back at least 1.4 m from the front and rear main walls (10.20.40.10(4)).
- Storeys: limited only where the Height Overlay Map shows an “ST” number (10.20.40.10(3)).
- Floor space index: the number after “d” in the zone label caps the house's floor area at that multiple of the lot area. On a 25 × 120 ft lot (about 279 m²) zoned d0.6, that is about 167 m² (1,800 sq ft), counted the by-law's way, which can leave out the basement and one parking space per unit (10.20.40.40(1), 10.5.40.40(3)).
- Length and depth: on lots with a required frontage of 18.0 m or less, the house may be no more than 17.0 m long, and its rear wall no more than 19.0 m back from the required front yard setback (10.20.40.20, 10.20.40.30). A second storey on the existing footprint doesn't make the house longer or deeper, but where the house is already past these limits, the zoning review checks how the new storey is treated.
- Balconies upstairs: no more than one platform on each side of the house and four in all, each up to 4.0 m² (10.20.40.50(1)).
Lot coverage counts the part of the lot covered by any part of a building, so a second storey built within the walls below adds none. One that cantilevers past them adds the overhang.
Setbacks you already have
Many Toronto houses sit closer to the side lot line than today's by-law allows. On a lot with frontage of 12.2 m (about 40 ft) or less, an addition above a lawfully existing house may keep the house's existing setbacks (10.5.40.71(3)). “Lawfully existing” includes buildings authorized or permitted on or before June 26, 2025, and those with a building permit lawfully issued before that date. On a wider lot, an addition has to meet today's setbacks, so a storey built straight up from a wall that's too close needs a minor variance (10.5.40.71(2)).
The floor space rule, and the secondary suite exemption
On many streets, floor space index is the number a full second storey breaks. Double a 90 m² bungalow on that 25 × 120 ft lot and the house reaches 180 m², past the 167 m² that d0.6 allows. By-law 848-2025, enacted July 24, 2025, says the zone's floor space index does not apply to a residential building with a secondary suite, or to a houseplex. It writes that into all five residential zones (R, RD, RS, RT and RM), to match the province's rules for additional units. In the RD, RS, RT and RM zones, where the Lot Coverage Overlay Map allows less than 45%, the same by-law lets a lot with a secondary suite be covered up to 45%.
So a house that will have a legal second unit, such as a basement apartment built under permit, isn't held to the “d” number. The suite has to be real: a self-contained unit with its own kitchen and bathroom, located in and subordinate to the main home, designed, permitted and inspected as a second unit, with the fire separation, exits and ceiling heights that come with it. Height, main walls and setbacks still apply. Our legal basement apartment guide covers what a suite needs.
Can the house carry a second storey?
A bungalow's foundation was built to hold one floor and a roof. The Building Code's basic table for house footings asks for strip footings 250 mm wide under exterior walls that carry one floor, and 350 mm under two, plus 65 mm for each storey of masonry veneer (brick or stone) over a wood frame. Under interior walls the same step is 200 mm to 350 mm, and a column footing at 3 m spacing goes from 0.40 m² to 0.75 m² (Table 9.15.3.4, 9.15.3.5). Where the joists span more than 4.9 m, the footing is sized by the Code's formula or by an engineering design under Part 4, and on gravel, sand or silt with the water table less than a footing's width below it, the widths double (9.15.3.3, 9.15.3.4).
These are the minimums for new construction. An existing footing is judged by what it can actually carry, which is why it gets checked rather than measured against the table alone.
So the first structural question is what's under the house now. We find the footing size where it can be seen, open a small test pit where it can't, and trace how the new load will come down through walls, beams and posts. Where the footings fall short, the drawings add new footings under the posts that carry the new load, or reinforce or underpin the foundation, to an engineer's design. Our underpinning guide covers that work.
The main floor's ceiling joists were sized for a ceiling, not a floor, so a second storey usually gets a new floor structure, often on new beams. Taking out or opening up walls on the main floor at the same time has its own rules, which our load-bearing wall guide covers.


When an engineer seals the structural sheets, on an eligible house project Toronto Building runs an expedited review of those parts and relies on the seal for their Building Code compliance, under its Reliance on Professional Engineer's Seal program. The engineer lists what they are responsible for on the City's Assumption of Responsibility for Engineering Content form.
Windows close to the lot line
On a narrow lot the new side walls sit close to the property line, and the Building Code treats them as a fire risk to the house next door. Where a wall is less than 1.2 m from the property line, the Code's table for houses allows no glazed openings in it, and the wall itself needs a fire-resistance rating (45 minutes is the usual route). Under 0.6 m, its cladding must also be noncombustible, such as metal, masonry or stucco, or one of the tested alternatives the Code lists (9.10.15.4, 9.10.15.5). Further away, the glass allowed grows with the distance. That's why second storeys on narrow Toronto lots take their windows at the front and back.
What the City asks to see
The application goes in as PDFs through Toronto Building's online Application Submission Tool. Every sheet is drawn to scale, fully dimensioned, signed and dated, and a qualified designer adds their name, registration number, qualification number and a statement taking responsibility for the design. For an addition, the City's guide asks for:
- Site plan on a current survey, with the setbacks to the property lines and the neighbouring buildings, and a summary of the zoning numbers, permitted and proposed: lot area, floor area, coverage, and the grade elevations that confirm the height.
- Floor plans for each level, existing and proposed, with the uses of every room, smoke and carbon monoxide alarms, plumbing fixtures, and the foundation, walls and framing above.
- Roof plan with the roof structure, slopes, skylights and ventilation.
- Elevations with finishes, window sizes and sill heights, the overall height, and the wall area, glazed openings and limiting distance on each side.
- Sections through the floor, wall and roof assemblies, with footing and foundation details and the floor-to-floor and overall heights.
- Forms: the Application to Construct or Demolish; the Energy Efficiency Design Summary, which every addition to a house needs; Schedule 1 Designer Information, from designers other than engineers and architects; the Assumption of Responsibility for Engineering Content form for sealed sheets; the Tree Declaration where trees could be damaged; the Rental Renovation Licence Screening Form; the overhead electrical conductors declaration, required with every addition; and the Municipal Road Damage form.
Additions of 100 m² or more, counting all the additions to the house together, also need a Residential Infill Construction Public Notice posted on the site. The owner or their agent asks Toronto Building for it with the Infill Public Notice Declaration form.
The City also runs a voluntary AI Pre-Check pilot for houses with up to two units, additions included. It flags likely gaps in an application before it is submitted. It doesn't approve anything or replace the City's review.
Heating the new floor
The Energy Efficiency Design Summary shows how the addition meets the Code's energy rules (Supplemental Standard SB-12). We also work out the heat loss of the new floor and lay out its ducts, so the furnace is checked against the bigger house before the walls close.
What a second-storey addition costs
The cost has four parts: the City's charges, the design, the engineer and the construction.
The City's charges
In 2026 the building permit for an addition to a house, semi or townhouse is $18.56 per m² of new floor area, with a $214.79 minimum. The area is measured to the outside face of the exterior walls, and balconies and habitable attic space count. No permit is issued until the City's fees are paid.
| New floor area | City fee |
|---|---|
| 60 m² (646 sq ft) | $1,113.60 |
| 80 m² (861 sq ft) | $1,484.80 |
| 100 m² (1,076 sq ft) | $1,856.00 |
| 120 m² (1,292 sq ft) | $2,227.20 |
- Work on the existing house: the $18.56 rate covers the new floor area. Where the floors below are altered, for a new stair or moved walls, the City charges the area affected at the interior alterations rate, $11.53 per m².
- Zoning Applicable Law Certificate: $644.38, not refunded once the review starts. A House Stream application without one is incomplete and has no review clock. Apply for the permit with it and the $644.38 is credited to the permit fee.
- Road damage deposit: $3,384.29, collected with the permit application. The City refunds it on request within two years of the work being completed, less a $95.01 fee and the cost of any damage to the road, curb or sidewalk.
- Plumbing and heating: no extra fee when the plumbing and HVAC permits are filed with the building permit, unless the heating is a specialty system. The City's stand-alone rates apply to work filed on its own.
- If the project adds a secondary suite: the City adds $56.33 for each new unit in the application.
- Minor variance, only if needed: $2,228.98 to the Committee of Adjustment for additions to a house with three units or fewer, and double that for a variance after the fact.
- Starting before the permit is issued: an extra 50% of the permit fee or $214.79, whichever is greater, up to $29,456.99 per permit.
- Development charges: no City development charges for enlarging an existing home: provincial law exempts the enlargement of an existing dwelling unit. Adding units has exemptions of its own, checked project by project.
Put together, the City's permit fees for an 80 m² second storey start at $1,484.80, with the zoning certificate counted inside that figure, plus the road damage deposit, which comes back if the street is left as it was.
Design, engineering and construction
We quote the design and permit set in writing after the zoning review, and the engineer's own fee is quoted alongside it. The construction cost depends mostly on these:
- Size and shape: the new floor area, and whether the storey covers the whole house or part of it.
- The roof: the old roof comes off, and the house needs protecting from the weather until the new one is closed in.
- The foundation: whether the footings carry two floors as they are, or need new footings, reinforcing or underpinning.
- The new floor: new joists and beams where the old ceiling can't serve as a floor, with steel where the spans are long.
- The stairs: a new stair takes room on both floors and can move rooms around on the main floor.
- Heating and plumbing: whether the furnace can heat the bigger house, and how far the new bathrooms are from the drain stack.
- A narrow lot: fire-rated side walls, noncombustible cladding close to the line, and little room to bring materials in.
- Living elsewhere: with the roof off, many families move out for part of the job.


How long it takes
The City sets clocks for some of these steps; the design and the build depend on the house.
- 01Zoning review
From the address and the survey, we check the zone label, the height and coverage overlays and any lawful setback the house can keep, and tell you in writing how we read them: what should fit without a variance. The City's own zoning review then confirms it.
- 02Measure and design
We measure the house as it stands, check what's under it, and design the new floor with you: rooms, stairs, roof, windows, and how the old and new floors meet.
- 03Minor variance, only if needed
If a number doesn't fit, the application goes to the Committee of Adjustment by email, with the plans, the City's forms, a zoning review of the plans (or the City's waiver form), a tree declaration and photos of the front and rear yards. The Committee holds a hearing. Once it decides, there are 20 days for an appeal to the Toronto Local Appeal Body before the decision is final, and since November 28, 2022 only the applicant, the Minister, specified persons and public bodies can appeal.
- 04Zoning certificate
The City checks the drawings against the zoning and other applicable law and issues the Zoning Applicable Law Certificate. One application includes up to three reviews.
- 05Permit review
Additions aren't among the projects that qualify for Express Services. A house with up to two units goes to the House Stream, where a complete application, with the certificate issued and the fees paid, is reviewed within 10 business days.
- 06Construction and inspections
The inspections include the footings, when the forms are in and before any concrete; the foundations; the structural framing, with plumbing and heating roughed in; fire separations, where the work has them, before the finishes go on; the insulation and vapour barrier; separate plumbing and heating inspections; and the final inspections inside and out. The City inspects within two business days of a request, and the stamped permit plans have to be on site.
- 07Close the permit
The owner books the final inspection when the work is done. The City warns that an open permit can get in the way of a later sale or a new permit.
One more timing point: while a permit for an addition is open, other work on the same house, such as underpinning or interior alterations, can't use Express Services either.
Where to start
Find the survey if you have one, and the house's original drawings if they exist. Photograph the house from the front, back and sides, and the basement walls. Send the address through our additions page. Rocco reads the zoning and replies in writing with what should fit, the drawings you need and a quote.
Questions people ask
01How much does a second-storey addition cost in Toronto?
The City's 2026 permit fee is $18.56 per m² of new floor area, so an 80 m² second storey (about 860 sq ft) is $1,484.80, and the $644.38 zoning certificate fee is credited against it. Changes to the floors below are charged on the area affected at $11.53 per m², and there is a $3,384.29 road damage deposit, refunded less $95.01 if the street is left undamaged. On top of that come the design and permit drawings, the engineer and the construction, which depends most on the size, the roof, whether the foundation needs work, the stairs, and the heating and plumbing.
02Do I need a permit for a second-storey addition in Toronto?
Yes. Toronto Building issues a building permit for an addition to a house, semi or townhouse. The application goes in as PDFs through the City's online tool, with a site plan on a survey, floor plans, a roof plan, elevations, sections and the forms, including the Energy Efficiency Design Summary. To be complete, it also needs an issued Zoning Applicable Law Certificate.
03How tall can a second storey be in Toronto?
In Residential Detached (RD) zones the limit is the number on the City's Height Overlay Map, or 10.0 m where the map shows none. The main walls are capped lower, at the higher of 7.0 m or 2.5 m below the height limit: 7.5 m under a 10.0 m limit. At least 70% of each side wall has to stay at or under that cap, or else 40% to 60% of the front and rear walls, depending on frontage. Other zones and site-specific exceptions have their own figures.
04Can my bungalow's foundation support a second storey?
It has to be checked. The Building Code's basic footing table asks for 250 mm strip footings under exterior walls carrying one floor and 350 mm under two, plus 65 mm for each storey of masonry veneer over a wood frame. The footings are found and measured, and where they fall short the drawings add new footings under the posts that carry the new load, or reinforce or underpin the foundation to an engineer's design.
05Do I need a minor variance for a second storey?
Only if the design breaks a zoning number, most often the floor space index, the height, the main wall height or a setback. On lots with frontage of 12.2 m or less, an addition above a lawfully existing house may keep its existing setbacks. Since By-law 848-2025, the floor space index doesn't apply to a house with a secondary suite. A variance for an addition costs $2,228.98 at the Committee of Adjustment in 2026.
06How long does a permit for a second-storey addition take?
Additions don't qualify for the City's 3-day Express Services. In the House Stream, a complete application is reviewed within 10 business days, and it is complete only with an issued Zoning Applicable Law Certificate and the fees paid. If a minor variance is needed, the Committee of Adjustment hearing comes first, and its decision is final once the 20-day appeal period passes without an appeal.
Sources
- 01Toronto Building: Small Residential Additions permit guide (opens in a new tab)
- 02Toronto Building: building permit fees (effective January 1, 2026) (opens in a new tab)
- 03Toronto Building: Zoning Applicable Law Certificate (opens in a new tab)
- 04Toronto Building: Building Permit Review Streams (opens in a new tab)
- 05Toronto Building: Building Permit Application Pre-Check (AI pilot) (opens in a new tab)
- 06Toronto Building: When to Call for Inspection of Small Buildings (opens in a new tab)
- 07Zoning By-law 569-2013, Chapter 10.20 Residential Detached Zone (s. 10.20.30.40, 10.20.40.10, 10.20.40.40, 10.20.40.50) (opens in a new tab)
- 08Zoning By-law 569-2013, Chapter 10 Residential (s. 10.5.40.71 and the June 26, 2025 lawfully existing date) (opens in a new tab)
- 09Zoning By-law 569-2013, Chapter 800 Definitions (lot coverage, secondary suite) (opens in a new tab)
- 10City of Toronto By-law 848-2025 (additional residential units: floor space index and lot coverage) (opens in a new tab)
- 11Committee of Adjustment: forms, submission guidelines and fees (2026) (opens in a new tab)
- 12Planning Act, R.S.O. 1990, c. P.13, s. 45(12) (appeal of a minor variance decision) (opens in a new tab)
- 132024 Building Code Compendium, Div. B, Part 9 (Articles 9.10.15.4, 9.10.15.5, 9.15.3.3 to 9.15.3.5, Table 9.15.3.4) (opens in a new tab)
- 14Toronto Municipal Code Chapter 519, Infill Construction, Public Notice (By-law 801-2018, as amended by By-law 1645-2019) (opens in a new tab)
- 15City of Toronto: Municipal Road Damage Deposit permit (2026 rates) (opens in a new tab)
- 16Toronto Building: Related Plumbing & Drain Permits (fees) (opens in a new tab)
- 17Toronto Building: Related Mechanical (HVAC) Permit (fees) (opens in a new tab)
- 18City of Toronto: Frequently Asked Questions About Development Charges (opens in a new tab)
- 19Ontario: calculating land transfer tax (opens in a new tab)
- 20City of Toronto: Municipal Land Transfer Tax rates and fees (opens in a new tab)
Rules and fees change. We verify them on every project before drawings start.





